Bridge Design and Construction Statistics
Bridge Length, Width, Height, Weight
Bridge Deflection, Load Capacity
Main Tower Stats
Main Cable StatsSuspender Rope (vertical ones) Stats
Concrete Quantities
Structural Steel Quantities
Length, Width, Height, WeightTotal length of Bridge including approaches from abutment to abutment: 1.7 miles = 8,981 ft = 2,737 m Total length of Bridge including approaches from abutment to abutment, plus the distance to the Toll Plaza: 9,150 ft = 2,788 m Length of suspension span including main span and side spans: 1.2 miles = 6,450 ft = 1,966 m Length of main span portion of suspended structure (distance between towers): 4,200 ft = 1,280 m Length of one side span: 1,125 ft = 343 m Width of Bridge: 90 ft = 27 m Width of roadway between curbs: 62 ft = 19 m Width of sidewalk: 10 ft = 3 m Clearance above mean higher high water: 220 ft = 67 m Total weight of each anchorage: 60,000 tons = 54,400,000 kg Original combined weight of Bridge, anchorages, and approaches: 894,500 tons = 811,500,000 kg Total weight of Bridge, anchorages, and approaches (1937): 894,500 tons = 811,500,000 kg Total weight of Bridge, anchorages, and approaches (1986)*: 887,000 tons = 804,700,00 kg* Weight of Bridge, excluding anchorages and approaches, and including the suspended structure, main towers, piers and fenders, bottom lateral system and orthotropic redecking (1986): 419,800 tons = 380,800,000 kg*
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Bridge Deflection, Load Capacity*Maximum transverse deflection, at center span: 27.7 ft = 8.4 m Maximum downward deflection, at center span: 10.8 ft = 3.3 m Maximum upward deflection, at center span: 5.8 ft = 1.77 m Live load capacity per lineal foot: 4,000 lbs. = 1,814.4 kg As an example of how the Bridge is built to move, during the winter storms in 1982, the main span bowed approximately 6 to 7 feet The three maximum deflections noted above at the center of the suspension bridge are due to the following loading conditions:
Main Tower StatsThe Golden Gate Bridge has two main towers that support the two main cables. Height of tower above water: 746 ft = 227 m Height of tower above roadway: 500 ft = 152 m Tower base dimension (each leg): 33 x 54 ft = 10 x 16 m Load on each tower from main cables: 61,500 tons = 56,000,000 kg Weight of both main towers: 44,000 tons = 40,200,000 kg Transverse deflection of towers: 12.5 inches = 0.32 m Longitudinal deflection of towers: shoreward: 22 in = 0.56 m and channelward: 18 in = 0.46 m The south tower foundation depth below mean low water is: 110 ft = 34m To build south tower pier to support the south tower, construction workers pumped 9.41 million gallons or 35.6 million liters of water out of the fender that was constructed first.
Main Cable StatsThe Golden Gate Bridge has two main cables which pass over the tops of the two main towers and are secured at either end in giant anchorages. The main cables rest on top of the 746-foot main towers in huge steel castings called saddles. Diameter of one main cable including the exterior wrapping: 36 3/8 in. = .92 m Length of one main cable: 7,650 ft = 2,332 m Total length of galvanized steel wire used in both main cables: 80,000 mi = 129,000 km Number of galvanized steel wires in one main cable that are 0.192 inches in diameter: 27,572 Number of bundles or strands of galvanized steel wire in one main cable: 61 Weight of both main cables, suspender cables and accessories: 24,500 tons = 22,200,000 kg The galvanized steel wire comprising each main cable was laid by spinning the wire using a loom-type shuttle that moved back and forth as it laid the wire in place to form the cables. The spinning of the main cable wires was completed in 6 months and 9 days. The galvanized steel wire used for the main cables is carbon steel with the following average chemical composition and physical properties:
Suspender Rope (vertical ones) StatsThe Golden Gate Bridge has a total of 250 pairs of vertical suspender ropes. Each suspender rope is 2 11/16 in. in diameter. All of the ropes were replaced between 1972 and 1976, with the last rope replacement completed on May 4, 1976. Concrete Quantities
Structural Steel Quantities
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||